The Leonard
Project
All about the Project
This is a whole first-floor remodel started in late August 2025. The centerpiece is opening up the living room with a flush 25' LVL beam. That requires temporary shoring, foundation footers and a raised foyer ceiling. A new stone fireplace and finished ceiling beams complete the room.
The kitchen and pantry are fully renovated, with a stone-clad hood and custom cabinetry throughout. Four bathrooms are reworked. The master bath gets a new window, double door, freestanding tub and tiled shower. The guest bath gets a new shower, and the hallway bath gets a lighter refresh. The laundry moves into the master suite, and the old laundry becomes a canning room.
The proposal also includes new plumbing, electrical and HVAC adjustments, drywall, trim, hardwood refinishing with new flooring at the back door, and first-floor painting. It included project management , dumpster, porta-john and cleanup, plus contingencies for subfloor repair, ducts and gas lines.

Project Timeline
28-32 weeks
Project Overview
Structural, Framing & Exterior
-
Demo & Prep: Basic demolition in the kitchen/pantry, the master bath and its connected second bath (becoming the new laundry), the old laundry (becoming the canning room), the guest bath, the hallway bath, and the living room/hallway tile. Includes site prep with plastic, floor protection and barriers. Wallpaper removal is excluded.
-
Framing & Structural:
-
A flush 25' LVL in the living room for the open concept, with temporary walls, existing posts removed and new foundation footers.
-
Interior wall framing for the chimney, kitchen, bathrooms and laundry.
-
Raised foyer headers, case openings and ceiling.
-
A window and double-door opening in the master bath, plus a hood soffit adjustment.
-
Sliding door framing, still unpriced while the door choice is pending.
-
-
Exterior & Roofing: A new white vinyl picture window in the master bath and a roof boot for the hood duct.
Mechanical, Electrical & Plumbing (MEP)
-
Plumbing & Gas:
-
Kitchen sink, dishwasher, pot filler, disposal and fridge line.
-
Pantry and whiskey room bar sinks.
-
A full redo of the master shower, freestanding tub and sinks.
-
Laundry relocation with a washer box and sink, and a commercial-style double-basin sink in the canning room.
-
Guest bath rework (shower drain, tub removed, 2 sinks, toilet reset), and a new toilet and faucet in the hallway bath.
-
A stovetop gas line, plus a gas line contingency at the fireplace.
-
-
HVAC: A kitchen hood vent line, relocating the living room return and ducts to make room for the office, and a contingency for moving ducts throughout the house.
-
Electrical:
-
Removing intercoms and old fixtures, installing owner-provided fixtures, and new standard switches and outlets.
-
Up to 3 bath fan/light combos and a kitchen rework.
-
6 new can lights in the living room and all downstairs ceiling fans.
-
Low-voltage wiring at the fireplace.
-
Separate per-unit contingency rates for extra can lights, outlets and fans.
-
Insulation, Drywall & Millwork
-
Insulation & Drywall: Insulation in the master bath and the LVL area. Drywall repair throughout, including the LVL, the raised ceiling and the fireplace detail.
-
Trim & Doors:
-
Basic trim (baseboard, crown, casings) in every room.
-
A master bath interior double door, a laundry sliding barn door, and shiplap in the canning room.
-
A guest linen closet build.
-
Front door install with new foyer case openings (the door itself is designer-selected and not priced).
-
-
Fireplace & Ceiling Beams: Stone on the fireplace and the hood face (the corbel detail is still pending), custom stained shelves, bench and mantle, and built living room ceiling beams with a finished wrap.
Cabinetry, Finishes & Surfaces
-
Cabinetry: Custom cabinets for the kitchen and island, whiskey room, pantry, master bath (with a pass-through to the laundry), laundry, canning room (still being finalized with plan changes) and guest bath. Install of the client-provided hallway vanity.
-
Countertops & Appliances: Countertops are $0 allowances in every room, coordinated by Sandy. Appliance install is still to be priced, and we recommend the suppliers install them.
-
Tile & Flooring:
-
Pantry backsplash.
-
Master shower walls, floor, pan, 2 niches and the tub surround.
-
Guest shower with a pan, niche and bench.
-
Canning room floor, plus hallway floor tile that also covers the hallway bath.
-
Hardwood refinish of about 1,760 sq ft, plus new matching wood flooring near the back door.
-
-
Paint: Prep and paint the entire first floor, including the barn door.
Management & Site Logistics
-
Administrative & Overhead: Project management fee. No permit line appears in this proposal.
-
Site Services: Dumpster (Griffin Waste), porta-john (Fusion Site) and professional cleanup during and after construction.
-
Contingencies: Subfloor repair (labor and materials).
Kitchen
![]() | ![]() | ![]() | ![]() |
|---|
Primary bath
![]() | ![]() | ![]() |
|---|
bathrooms
![]() | ![]() | ![]() | ![]() | ![]() |
|---|