The Leonard
Project

All about the Project

This is a whole first-floor remodel started in late August 2025. The centerpiece is opening up the living room with a flush 25' LVL beam. That requires temporary shoring, foundation footers and a raised foyer ceiling. A new stone fireplace and finished ceiling beams complete the room.
The kitchen and pantry are fully renovated, with a stone-clad hood and custom cabinetry throughout. Four bathrooms are reworked. The master bath gets a new window, double door, freestanding tub and tiled shower. The guest bath gets a new shower, and the hallway bath gets a lighter refresh. The laundry moves into the master suite, and the old laundry becomes a canning room.

The proposal also includes new plumbing, electrical and HVAC adjustments, drywall, trim, hardwood refinishing with new flooring at the back door, and first-floor painting. It included project management , dumpster, porta-john and cleanup, plus contingencies for subfloor repair, ducts and gas lines.
IMG_2745.heic

Project Timeline

28-32 weeks

Project Overview

Structural, Framing & Exterior

  • Demo & Prep: Basic demolition in the kitchen/pantry, the master bath and its connected second bath (becoming the new laundry), the old laundry (becoming the canning room), the guest bath, the hallway bath, and the living room/hallway tile. Includes site prep with plastic, floor protection and barriers. Wallpaper removal is excluded.

  • Framing & Structural:

    • A flush 25' LVL in the living room for the open concept, with temporary walls, existing posts removed and new foundation footers.

    • Interior wall framing for the chimney, kitchen, bathrooms and laundry.

    • Raised foyer headers, case openings and ceiling.

    • A window and double-door opening in the master bath, plus a hood soffit adjustment.

    • Sliding door framing, still unpriced while the door choice is pending.

  • Exterior & Roofing: A new white vinyl picture window in the master bath and a roof boot for the hood duct.

​

Mechanical, Electrical & Plumbing (MEP)

  • Plumbing & Gas:

    • Kitchen sink, dishwasher, pot filler, disposal and fridge line.

    • Pantry and whiskey room bar sinks.

    • A full redo of the master shower, freestanding tub and sinks.

    • Laundry relocation with a washer box and sink, and a commercial-style double-basin sink in the canning room.

    • Guest bath rework (shower drain, tub removed, 2 sinks, toilet reset), and a new toilet and faucet in the hallway bath.

    • A stovetop gas line, plus a gas line contingency at the fireplace.

  • HVAC: A kitchen hood vent line, relocating the living room return and ducts to make room for the office, and a contingency for moving ducts throughout the house.

  • Electrical:

    • Removing intercoms and old fixtures, installing owner-provided fixtures, and new standard switches and outlets.

    • Up to 3 bath fan/light combos and a kitchen rework.

    • 6 new can lights in the living room and all downstairs ceiling fans.

    • Low-voltage wiring at the fireplace.

    • Separate per-unit contingency rates for extra can lights, outlets and fans.

 

Insulation, Drywall & Millwork

  • Insulation & Drywall: Insulation in the master bath and the LVL area. Drywall repair throughout, including the LVL, the raised ceiling and the fireplace detail.

  • Trim & Doors:

    • Basic trim (baseboard, crown, casings) in every room.

    • A master bath interior double door, a laundry sliding barn door, and shiplap in the canning room.

    • A guest linen closet build.

    • Front door install with new foyer case openings (the door itself is designer-selected and not priced).

  • Fireplace & Ceiling Beams: Stone on the fireplace and the hood face (the corbel detail is still pending), custom stained shelves, bench and mantle, and built living room ceiling beams with a finished wrap.

 

Cabinetry, Finishes & Surfaces

  • Cabinetry: Custom cabinets for the kitchen and island, whiskey room, pantry, master bath (with a pass-through to the laundry), laundry, canning room (still being finalized with plan changes) and guest bath. Install of the client-provided hallway vanity.

  • Countertops & Appliances: Countertops are $0 allowances in every room, coordinated by Sandy. Appliance install is still to be priced, and we recommend the suppliers install them.

  • Tile & Flooring:

    • Pantry backsplash.

    • Master shower walls, floor, pan, 2 niches and the tub surround.

    • Guest shower with a pan, niche and bench.

    • Canning room floor, plus hallway floor tile that also covers the hallway bath.

    • Hardwood refinish of about 1,760 sq ft, plus new matching wood flooring near the back door.

  • Paint: Prep and paint the entire first floor, including the barn door.

 

Management & Site Logistics

  • Administrative & Overhead: Project management fee. No permit line appears in this proposal.

  • Site Services: Dumpster (Griffin Waste), porta-john (Fusion Site) and professional cleanup during and after construction.

  • Contingencies: Subfloor repair (labor and materials).

Kitchen

IMG_2745
IMG_2746
IMG_2824
IMG_2747

Primary bath

IMG_2752
IMG_2751
IMG_2750

bathrooms

IMG_1144
IMG_1146
IMG_1145
IMG_2758
IMG_2759
Bread in Tote

Hard Cost:

$275,000- $300,000

Selections:

$85,000-$150,000

Range:

$360,000 - $450,000