All about the Project

Conversion of the garage into finished living space with a bathroom covering demolition; framing including structural-engineer-recommended reinforcement, plywood sheathing, and a gable vent; roofing repair and duct work; new windows plus a bathroom transom; a French door with hardware; siding and siding materials; plumbing rough-in and water heater install; electrical with requested extras; a Mr. Cool 18,000 BTU mini-split plus a separately purchased and installed HVAC unit; batt and blown insulation.

Atfer Drywall- finishes include custom cabinets; LVP flooring; the bathroom tile package with shower pan, shampoo box, grab bar, and glass frame; interior trim including split-jamb doors and a beadboard addition; interior and exterior painting; hardware install; and cleanup, dumpster, porta-john, permits, engineering fee, and project management.

Project Timeline

The completion of this project from start to finish:

14 weeks

Project Overview

  • Scope: Conversion of a garage into a finished living space complete with a full bathroom.

 

Structural, Exterior & Roofing

  • Demolition & Framing: Initial demolition, framing with structural-engineer-recommended reinforcement, plywood sheathing, and a gable vent.

  • Exterior & Openings: Siding and siding materials, roof repair, new windows, a bathroom transom, and a French door with hardware.

​

Mechanical, Electrical & Plumbing (MEP)

  • Plumbing: Plumbing rough-in and water heater installation.

  • HVAC: Mr. Cool 18,000 BTU mini-split, a second separately purchased/installed HVAC unit, and ductwork.

  • Electrical: Electrical installation including client-requested extras.

​

Interior Finishes & Fixtures

  • Insulation & Drywall: Batt and blown insulation, hanging and finishing drywall.

  • Cabinetry & Flooring: Custom cabinets and LVP flooring.

  • Bathroom Package: Tile package with shower pan, shampoo box, grab bar, and glass frame.

  • Trim & Paint: Interior trim (including split-jamb doors and beadboard addition), interior and exterior painting, and hardware installation.

​

Management & Site Logistics

  • Administrative & Overhead: Permits, structural engineering fee, and project management.

  • Site Services: General cleanup, dumpster rental, and porta-john service.

Kichenette

IMG_1798
IMG_1796
IMG_2145
Bread in Tote

Hard Cost:

Selections:

$8,963.70

Range:

$106,647.19